The site team have been hard at work the last couple of
weeks erecting the scaffolding inside and outside the swimming pool area.
The reduced level of excavations along with all of the
foundations and underpinning have been completed on site. Concrete columns
surrounding the pool area have been prepared and bolts set for steel portals.
Due to complications with paint specifications we were
unable to erect the steel frame on schedule. However, the problem has been
resolved and the programme has not been affected by the delay.
Our guys have definitely been lucky with the weather this week as the steel frame arrives!
The pre-cast concrete floor beams to the first floor area
are programmed for installation on the 22nd August 2016 for two
days. For this reason, the Halo leisure swimming pool car park will be closed
between 22/08/16 – 24/08/16.